Residents force commissioner to put off meet

Residents force commissioner to put off meet
The Hindu.com - Staff Correspondent

HDMC had convened the consultation meeting on 24x7 Water Supply Project
--------------------------------------------------------------------------------
# No move to privatise water supply system: Mr. Manivannan
# Another meeting will be held next Sunday
--------------------------------------------------------------------------------

IN CONTENTION: Residents of Dharwad arguing with Hubli-Dharwad Municipal Corporation commissioner P. Manivannan at a meeting on Sunday.



DHARWAD: The consultation meeting with the residents of Dharwad regarding the 24x7 Water Supply Project, convened by Hubli-Dharwad Municipal Corporation (HDMC) here on Sunday, was put off following opposition from the residents.

The residents complained that they were not being properly informed about the project, including the water tariff fixing mechanism.

The 24x7 Water Supply Project, is being implemented as a pilot project in four wards each in Hubli and Dharwad by the Karnataka Urban Infrastructure Development Finance Corporation.

The project is also being implemented in Belgaum and Gulbarga. The pilot project, which was to become functional in the twin cities by November, had been delayed due to opposition from a section of residents.

The Sunday's meeting, at Nandikol Basaveshwara Temple in Mangalwarpet, was organised to clarify the doubts raised by the residents.

However, the residents did not allow the Municipal Commissioner P. Manivannan to clarify their doubts.

The residents, led by members of "Neeru Khasagikarana Virodhi Samiti" (Anti Water Privatisation Committee) said that the water supply system was being handed over to a foreign company.

This would result in people struggling for water everyday, they added. They said that once the water supply system was handed over to the foreign company for maintenance, the HDMC would lose control over fixing the tariff. They urged Mr. Manivannan to stop the project.

No privatisation

Mr. Manivannan informed the residents that there was no move to privatise the water supply system. He said the foreign company Companie Generale Desaux would only do the maintenance work and the Corporation would have the final say in fixing the tariff. He said that the company would handover the maintenance work to the corporation after two years. The State Government had set up a committee for fixing water tariff, he added.

Despite the assurances, the samiti members and the residents forced Mr. Manivannan to put off the meeting.

Another meeting will be held on December 3 at Kalabhavan in Dharwad.

Sunday, November 26, 2006

DC to give report on land for airport work

DC to give report on land for airport work
The Hindu - Staff Correspondent

--------------------------------------------------------------------------------
# Plan to develop airport according to global standards
# Deputy Commissioner to meet with residents of the area
--------------------------------------------------------------------------------
DHARWAD: Deputy Commissioner of Dharwad M.S. Srikar will submit a report within a week on the acquisition of 650 acres of land for the expansion of the Hubli airport.

This follows a high-level meeting convened by Tourism and Infrastructure Development Minister B. Sriramulu in Bangalore recently, involving Revenue Minister Jagadish Shettar, Pralhad Joshi, MP, senior officials of the Airports Authority of India (AAI) and Mr. Srikar.

The AAI had submitted in September two revised master plans for making the airport an all-weather one. While the first was for acquiring an estimated 446 acres of land for facilitating the operations of an Airbus-320, the other was for developing the airport according to international standards and making it suitable for handling big flights.

Mr. Srikar told The Hindu he had been asked to submit the report at the earliest and he would be doing so within a week. He had presented an initial report at the meeting based on the revised plans for the airport and would now submit a detailed plan along with the ground survey report.

Demolition

The number of houses that would be demolished for the airport's expansion would be less than a 100. The earlier plan submitted by the AAI had said that more than 500 houses would need to be demolished. However, the officials had revised the plan after an appeal was made by the district-in-charge Minister and the district administration, Mr. Srikar said.

Responsibility

The district administration had suggested at the meeting that the responsibility of acquiring the land be handed over to the Karnataka Industrial Area Development Board (KIADB), he said. Approximately Rs. 150 crore would be required for the acquisition of the land. Mr. Srikar said he would be holding a meeting next week with the residents of the area whose houses would be demolished to facilitate the expansion of the Hubli airport.

Water supply project to take off in Dec

Water supply project to take off in Dec
TIMES NEWS NETWORK - M L Kapur

25 Nov, 2006 2302hrs IST

HUBLI: The project to supply drinking water 24x7 in select wards of Hubli is finally all set to be commissioned by mid-December.

It was initially planned to be operative by September-end.

However, it has hit a roadblock in four of the selected wards in Dharwad due to opposition from certain groups coupled with lack of awareness about the scheme and poor paying capacity of beneficiaries.

Funded by Asian Development Bank, the project is being implemented by Karnataka Urban Infrastructure Development Finance Corporation (KUIDFC). This demonstration project has been taken up in Hubli-Dharwad, Belgaum and Gulbarga.

In all, about 9,000 households are to be covered under the project in Hubli-Dharwad and nearly 4,000 each in Belgaum and Gulbarga. Some 2,500 connections will be given in Hubli initially, and the twin-cities are likely to be covered by March-end next year.

According to officials associated with the implementation of the project, nearly 400 connections have become operational in Belgaum where water is being supplied up to the third floor. However, the project is facing some resistance in Gulbarga also.

Project officials attribute apprehensions about acceptance of this novel scheme in the state to the inability of NGOs entrusted with the task of creating awareness about it among the potential beneficiaries.

They say that households covered under it feel that water supply was being privatised and that they may have to pay much more once it was implemented.

In fact, the builder will operate the project for two years before handing it over to the respective civic bodies.

Dismissing apprehensions about the project, a representative of the builder-operator told TOI that probably there has been less than desired coordination between KUIDFC, Water Board and the civic bodies.

However, he said the residents covered so far under the project in Belgaum were happy that they were getting round-the-clock water supply up to third floors, "which was just unthinkable in the past."

They also save on the power required to pump water to upper floors.

However, he agreed that the consumers may end up paying slightly more than earlier, but claimed that people would not mind the burden as it was more than compensated by the quality of service.

He said: "It would mean tension free regular supply at full pressure compared to the uncertain supply at odd hours as at present. There would be no need for storage and it would also curb wastage of water in the long run.

Friday, November 24, 2006

Dharwad Utsav to be annual affair

Dharwad Utsav to be annual affair
Business Standard Reporter / Chennai

(photo source:dharwadutsav.com)
Dharwad November 24, 2006

Egged on by the tremendous success of Dharwad Utsav and the response from the cultural circles and people at large, the Dharwad district administration has decided to make Dharwad Utsav a regular annual feature.

Dharwad Deputy Commissioner M S Srikar, who spearheaded the Dharwad Utsav-2006, said a good beginning had been made in the Suvarna Karnataka year and from next year onwards the festival will be on a still larger scale on the lines of Mysore Dasara, Bangalore Habba and Hampi Utsav.

For the funds, he said sponsorship from the corporate sector and the government will be sought. The three-day Dharwad Utsav-2006 was held on November 17, 18 and 19 was a grand success.

“The aim was to create a brand image and it has been proved that we have the capacity to organise the event in a grand manner,” said Srikar.

The state government had sanctioned Rs 15 lakh for the three-day Utsav being held after seven long years. The festival offered a veritable treat to the people with a series of events to showcase the spirit of Dharwad.

Actor Naseeruddin Shah hogged the limelight with his performance in his play 'Ismat Apa Ke Naam' based on the life of the Urdu short story writer Ismat Chughtai.

The events were held simultaneously at 13 venues in Dharwad and Hubli. Dance, drama, music, painting, art exhibition, folk, seminars, poetry meet, mimicry and processions added colour and fervour to the festival.

It proved to be a people's festival with a large number of people thronging the venues on all the three days.

Leading litterateurs, dancers, musicians, painters and artistes participated in the festival. The twin cities wore a festive look with buildings and monuments being illuminated.

An exhibition of musical instruments and photographs at the residence of Hindustani exponent Gangubai Hanagal in Deshpande Nagar of Hubli was a big hit.

The festival, besides providing a feast to the connoisseurs also provided a platform for talented youngsters to prove their mettle.

The Karnatak College grounds provided a perfect venue for the events in the backdrop of the imposing monumental main building, which was illuminated.